NHSRCL spokesperson Sushma Gaur said that the technical bids for contract packages of P-1(B) and P-1(C) for construction or building of bridges for the MAHSR corridor in the state of Gujarat as well union territory of Dadra and Nagar Haveli.
She said that as of now, 5 bidders for
She said that the P-1 (C) package includes construction of bridges for double line High Speed railway for four PSC Bridges and seven steel truss bridges between Zaroli Village at Maharashtra -- Gujarat Border and Vadodara, in Gujarat and the union territory of Dadar and Nagar Haveli for the project.
Gaur said that for the P-1 (C) package, Ranjit Buildcon Limited, MG Contractors Pvt Ltd, KEC-SAM India JV and GRIL-GPT JV have participated in the technical bids.
Meanwhile, package P-1 (B) includes the construction of bridges for double line high speed railway for one PSC Bridge and four steel truss bridges between Vadodara and
She said that Ranjit Buildcon Limited, MG Contractors Pvt Ltd, KEC-SAM India JV and GRIL-GPT JV and URC Construction Pvt Ltd have participated in the technical bids.
Prime Minister
Bullet trains are expected to run at 320 km per hour covering the 508-km stretch in about two hours. In comparison, trains currently plying on the route take over seven hours to travel the distance, whereas flights take about an hour.
SEE ALSO:
Apple’s new Find My feature updated to prevent stalking as launch of the rumoured AirTags nears
OPINION: Regulating digital news is important but freedom of press is precious
Heranba Industries makes a bumper debut on stock exchanges — shares soar 44% over the issue price band
EXCLUSIVE: Bankers may be working all 31 days of March with the government looking to double the loans doled out under the PM SVANidhi scheme