Stunning new images show how far London's Crossrail has come in the last year
© Crossrail Ltd
London's Crossrail project is now more than 70% complete after construction began in 2009.
The underground railway network will make getting around the city much faster and easier by reducing crowds on existing rail services, like the London Underground and National Rail.
Crossrail estimates the first services will begin in mid-2018, with the rest being opened in phases until December 2019.
So far, over 10 kilometres (6 miles) of new track has been installed according to a project overview, and at some stations, work is close to being finished.
Check out the latest images of the work that's being done to the multi-billion pound project.
- Saudi Arabia wants China to help fund its struggling $500 billion Neom megaproject. Investors may not be too excited.
- I spent $2,000 for 7 nights in a 179-square-foot room on one of the world's largest cruise ships. Take a look inside my cabin.
- One of the world's only 5-star airlines seems to be considering asking business-class passengers to bring their own cutlery
- Things to do in Goa in monsoon to make the most out of your trip
- Healthy choices for summer: 7 soups to support your weight loss goals
- India's pharma exports rise 10% to $27.9 bn in FY24
- Indian IT sector staring at 2nd straight year of muted revenue growth: Crisil
- Shubman Gill to play 100th IPL game as Gujarat locks horns with Delhi today