US Knowingly Purchased Faulty $5 Million Incinerators, Forcing Troops To Work Open-Air Burn Pits

Advertisement

Incinerator FOB Sharana

SIGAR

Two 40-Ton Capacity Incinerators at FOB Sharana

In the latest in a slew of attacks by government watchdogs on military reconstruction efforts and spending in Afghanistan, a newly released report has found that the U.S. Army Corps of Engineers (USACE) paid $5.4 million for waste incinerators that were riddled with deficiencies and declared so unsafe as to be inoperable.

Advertisement

As a result, troops and personnel at Forward Operating Base Sharana in Eastern Afghanistan were forced to use hazardous open-air burn pits to dispose of waste, a practice the military has acknowledged can cause temporary and longterm health problems.

The investigation, conducted by Special Inspector General for Afghanistan Reconstruction (SIGAR), found that in one instance, USACE paid a contractor for two facilities that were 30 months behind schedule, had known construction deficiencies, and were not tested to ensure operability before being installed. After the installation, a safety inspection found numerous electrical deficiencies that would cost approximately $1 million to repair, leading FOB Sharana officials to abandon the incinerators altogether and continue using the open-air pits.

SIGAR Inspector General John F. Sopko told Fox News, "I don't know what the U.S. Army Corps of Engineers considers success but spending more than $5 million dollars on something that was never used is not what I call successful to the American taxpayer."

incinerator loading area

SIGAR

The loading area for the incinerators

Based on a review of available documentation, SIGAR found that some of the delays in construction were attributable to security and weather. An additional year of delays could not be accounted for, however, though USACE officials stated that some of the hold up was due to contractor performance issues.

Advertisement

SIGAR said it had previously raised concerns "regarding instances in which USACE failed to hold its contractors accountable for not accomplishing work they were failed to perform."

Despite these problems, USACE paid the Denver-based contractor, International Home Finance & Development LLC), in full and installed the facilities without testing them at FOB Sharana.

"If the incinerator facility had been put into operation in August 2010, as planned," the report continues, "FOB Sharana would have been able to close its open-air burn pit. However, because of the delays and eventual acceptance of an unusable incinerator facility, base personnel faced continued exposure to potentially hazardous emissions, and $5.4 million of U.S. taxpayer dollars could have been put to better use."

"This project appears to have been a complete waste," Sopko told Fox. "Even worse, the open air burn pit used instead of the incinerators put the health of our troops at risk."

open air burn pit FOB Sharana

Flickr/SIGAR

Open-air burn pit at FOB Sharana

SIGAR has raised the issue of health risks associated with open-air burn pits before, most notably in a letter to the heads of CENTCOM on July 11, 2013 describing health and operation violations at open-air pits at Camp Leatherneck in Helmand province.

Advertisement

Safe waste elimination has been a source of concern in both Iraq and Afghanistan since the early 2000s.

A 2010 GAO study on open waste management in Iraq and Afghanistan found that oversight and operation of burn pits "varies substantially across installations," leading to uneven compliance with CENTCOM guidance on waste management and safety precautions.

In July 2013, Sens. Tom Udall (D-N.M) and Bob Corker (R-Tenn.) sent a letter to Sec. of Defense Chuck Hagel asking for immediate action to halt the use of open-air pits in Afghanistan and requesting that "service members who have been exposed to air pollution caused by the open-air burn pits be notified about the dangers of their exposure, and that their service records indicate that they have served in an area where open-air burn pits were used."

Health concerns associated with breathing the toxic smoke emissions from open-air burn pits include "reduced lung function and exacerbated chronic illness, ranging from asthma to chronic obstructive pulmonary disease," according to SIGAR findings.

open air burn pit

Flickr/SIGAR

Open-air burn pit emissions at FOB Sharana

Advertisement

In response to the investigation, USACE denied that any of the USACE contracting officers assigned to provide oversight on the contracts failed to perform their duties. As a result, it would take no action against any of the contracting personnel. SIGAR has requested documentation for these conclusions.

Since being sworn in as the head of SIGAR in 2012, former prosecutor John Sopko has reenergized a once-failed agency and has aggressively pursued instances of wasteful spending in a war effort that has received more than $95 billion from Congress since 2002.

Recent targets of investigation by Sopko's watchdog include a $34 million state-of-the-art facility built by the Pentagon in Helmand Province, a facility the Marine Corps said it never wanted nor intended to use.