Business Insider India has updated its Privacy and Cookie policy. We use cookies to ensure that we give you the better experience on our website. If you continue without changing your settings, we\'ll assume that you are happy to receive all cookies on the Business Insider India website. However, you can change your cookie setting at any time by clicking on our Cookie Policy at any time. You can also see our Privacy Policy.

Close
HomeQuizzoneWhatsappShare Flash Reads
 

This is what disappointment looks like for the Pentagon

May 26, 2016, 00:27 IST

Advertisement
An F-35B from Marine Fighter Attack Training Squadron 501 (VMFAT-501), flies near its base a MCAS Beaufort, South Carolina.Lockheed Martin

America's most expensive weapons system ever just hit another snag.

The F-35 Lightning II, Lockheed Martin's fifth-generation fighter jet, is expected to miss another crucial deadline on its march to combat readiness.

On Tuesday, the Pentagon acknowledged that the jet would stumble pass its operational testing phase.

"The target was the middle of 2017, but it's clear we're not going to make that," said Frank Kendall, the Pentagon's top acquisition officer said. 

The new schedule date, according to Kendall, is likely to occur in 2018.

Advertisement

The mid-2017 target was already a postponement from the original target date because of setbacks with the F-35's sixth and final software release, referred to as Block 3F.

The Block 3F software is part of the 8 million lines of sophisticated software code that underpin the F-35.

In short, if the code fails, the F-35 fails.

Lockheed Martin

The latest setback for the F-35 stems from a 48-page December 11 report from Michael Gilmore, the Pentagon's top weapons tester.

Advertisement

According to Gilmore, the stealth fighter won't be ready by its July 2017 deadline.

As first reported by Aviation Week, the DoD report says "the rate of deficiency correction has not kept pace with the discovery rate," meaning more problems than solutions are arising from the F-35 program.

"Examples of well-known significant problems include the immaturity of the Autonomic Logistics Information System (aka the IT backbone of the F-35), Block 3F avionics instability, and several reliability and maintainability problems with the aircraft and engine."

Airmen from the 33rd Maintenance Group perform checks on an F-35A Lightning II prior to a hot pit refueling session at Eglin Air Force Base, Florida.US Air Force Photo

One recommendation Gilmore gives for the F-35's latest woes is to triple the frequency of weapons-delivery-accuracy tests, which are executed once a month.

Advertisement

Adding more tests to the troubled warplane will most likely add to the cost overruns and schedule delays, but Gilmore says decreasing testing to meet deadlines will put "readiness for operational testing and employment in combat at significant risk."

According to the DoD report, the Block 3F software testing began in March, 11 months later than the planned date.

The Department of Defense's first F-35 aircraft soars over Destin, Fla., with an Air Force F-16 Fighting Falcon fighter aircraft before landing at its new home at Eglin Air Force Base, July 14, 2011.US Air Force

The nearly $400 billion weapons program was developed in 2001 to replace the US military's F-15, F-16,and F-18 aircraft.

Lockheed Martin's "jack-of-all-trades" F-35s were developed to dogfight, provide close air support, execute long-range bombing attacks, and take off from and land on aircraft carriers - all the while using the most advanced stealth capabilities available.

Advertisement

Adding to the complexity, Lockheed Martin agreed to design and manufacture three variant F-35s for different sister service branches.

The Air Force has the agile F-35A; the F-35B can take off and land without a runway, ideal for the amphibious Marine Corps; and the F-35C is meant to serve on the Navy's aircraft carriers. 

All three F-35 variants at Edwards Air Force Base, Calif. Left to right: F-35C carrier variant, F-35B short takeoff/vertical landing variant, F-35A conventional takeoff and landing variant.Lockheed Martin

Despite the Block 3F software setback, the Marine Corps last year declared an initial squadron of F-35s ready for combat, making it the first service branch to do so.

The standard for readiness the Marines used, referred to as initial operational capability, is determined separately by each service branch when the aircraft has successfully demonstrated various capabilities.

Advertisement

IOCs are announced prematurely, however, in that all tests and upgrades to the aircraft, such as the Block 3F software update, have not necessarily been completed.

Still, Gen. Joseph Dunford, then the commandant of the Marine Corps, in July declared initial operational capability for 10 F-35B fighter jets.

The Air Force is expected to declare IOC for its F-35As later this year, and the Navy plans to announce IOC for the F-35Cs in 2018.

Even so, America's most expensive warplane's turbulent march to combat readiness is far from over.

Advertisement
A Lockheed Martin Corp's F-35C Joint Strike Fighter is shown on the deck of the USS Nimitz aircraft carrier after making the plane's first ever carrier landing using its tailhook system, off the coast of California, November 3, 2014.REUTERS/Mike Blake

Here's the full report from the Department of Defense: