442 infrastructure projects report cost overrun of ₹4.34 lakh crore
Dec 27, 2020, 14:59 IST
New Delhi, As many as 442 infrastructure projects have reported a cost overrun of more than Rs 4.34 lakh crore as of December 1, according to the data from the Ministry of Statistics and Programme Implementation.
A report by the Ministry showed that 536 Central sector projects are delayed from their original schedules.
"Total original cost of implementation of the 1,671 projects was 21,21,383.82 crore and their anticipated completion cost is likely to be 25,55,957.52 crore, which reflects overall cost overruns of 4,34,573.70 crore (20.49% of original cost)," said the report.
The expenditure incurred on these projects till November 2020 is nearly ₹11.94 lakh crore, which is 46.71% of the anticipated cost of the projects.
It said that of the overall 1,671 Central sector infrastructure projects costing ₹150 crore and above, nine projects are ahead of the schedule, 184 are on schedule, 536 are delayed, 442 projects reported cost overrun and 212 projects reported both time and cost overrun with respect to their original project implementation schedules.
However, it said the number of delayed projects decreases to 412 if delay is calculated on the basis of latest schedule of completion.
Further, for 942 projects neither the year of commissioning nor the tentative gestation period has been reported.
SEE ALSO:
Mrs Bector’s Food IPO investors saw their money double on listing day
From taking on Yahoo to being tamed by China’s Communist Party— it’s been a roller coaster decade for Jack Ma
EY is looking to hire 9,000 techies in 2021 to boost its digital services
Advertisement
A report by the Ministry showed that 536 Central sector projects are delayed from their original schedules.
"Total original cost of implementation of the 1,671 projects was 21,21,383.82 crore and their anticipated completion cost is likely to be 25,55,957.52 crore, which reflects overall cost overruns of 4,34,573.70 crore (20.49% of original cost)," said the report.
The expenditure incurred on these projects till November 2020 is nearly ₹11.94 lakh crore, which is 46.71% of the anticipated cost of the projects.
It said that of the overall 1,671 Central sector infrastructure projects costing ₹150 crore and above, nine projects are ahead of the schedule, 184 are on schedule, 536 are delayed, 442 projects reported cost overrun and 212 projects reported both time and cost overrun with respect to their original project implementation schedules.
Advertisement
Further, for 942 projects neither the year of commissioning nor the tentative gestation period has been reported.
SEE ALSO:
Mrs Bector’s Food IPO investors saw their money double on listing day
From taking on Yahoo to being tamed by China’s Communist Party— it’s been a roller coaster decade for Jack Ma
EY is looking to hire 9,000 techies in 2021 to boost its digital services